Having issues with Sprint report. A story ticket was updated from previous sprint (Sprint Q4-2022 to Sprint Q1-2023). This sprint update was done before the current sprint Sprint Q1-2023 started.
But I see the story ticket in current Sprint report under "Issues removed from Sprint" section. Is that correct?
Pls Assist.
Thanks,
Pradeep
Yes, that's correct here.
As when you have the sprint report after completion; the reports will be accurate, and the removed entry doesn't affect sprint health