I am trying out the JIRA Agile functionality, and cannot figure out whether it is possible to estimate the time on a Task in the backlog. I can see that for a User Story there is an "Estimate" field, but it is missing for "Tasks". Any pointers?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
Woops just answered my own comment. In the configuration if I change Estimation to "Original Time Estimate" rather than "Story Points", I can now see the Estimate option on tasks as well. This is very un-intuitive. The unit of measuring progress should not dictate whether or not a field is visible in an Issue!