Time remaining calculation is incorrect

Walter Fawcett November 7, 2014

I have a task...

  • Original Estimate:  3d 1h
  • Time Spent:  3d 2h
  • Time Remaining:  1d 6h

It should show 0h or -1h remaining ... help...

 

image2014-11-7 5:56:35.png

2 answers

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2014

The time remaining is not always calculated based on Estimated - Logged. You have an option to update the time remaining when a time is logged (i.e. because the original estimate may not always be accurate).

Check the history tab to see if "Time remaining" was manually altered or not.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2014

Ah, no.   Estimated = 3d 1h.  That's not the original estimate, it's the current.  1d 6h left to go, and logged 3d 2h.  Have a look at the history, you should see the original esttmate is 4d 7h.

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, jira product discovery, jpd premium, product management, idea management, product discovery, jira premium, product planning, atlassian community, product development, roadmap planning, product prioritization, feature management

Introducing Jira Product Discovery Premium ✨

Jira Product Discovery Premium is now available! Get more visibility, control, and support to build products at scale.

Learn more
AUG Leaders

Atlassian Community Events