When I can write storypoints in jira?

Aizhan Kuanyshova
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 13, 2021

I have questions:
1)When I can write storypoints in jira?
2)Who should write storypoints to jira? Each member of the team need to fix it or just manager?


1 answer

2 votes
Ollie Guan
Community Champion
September 13, 2021

Hi @Aizhan Kuanyshova ,

Take the Scrum process as an example.

Usually, the team is delivered in the refinement (requirement clarification) meeting for size estimation (relative estimation, Fibonacci sequence, poker estimation), and after the team discusses the story points, the team members (I don’t think it is necessary to limit a specific role to operate) fill in the corresponding story points in Jira.

In Jira, you usually need to establish a sprint first, and then estimate the stories in order of priority.