When I move the jira task from developer to test how to manage USP

Karthik Giridharan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 9, 2021

The problem is as below

1. The story is created and assigned to a developer [Status: New]

2. User Story point are allocated as per estimation [Status: New]

3. Developer starts working on the story [Status: In Progress]

4. Developer moves to [Status: Code Review]

5. Developer changes the Assignee to QA [ Status: Ready for QA]

6. QA works on it and closes it [Status: Done]

 

problem statement: how do I track the effort of QA and DEV separately if that is possible in terms of Story Points when one story/task is moved between DEV and QA  as all tasks finally end up in QA bucket

1 answer

1 accepted

0 votes
Answer accepted
Robert Wen_Cprime_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 9, 2021

Hello @Karthik Giridharan ! Welcome to the Atlassian Community!

Story points should be an estimate of TEAM effort to complete a story, including development, QA, and deployment.

I wouldn't try to try to divide up story points between different efforts.

I also include this interesting article: https://medium.com/contino-engineering/you-are-using-story-points-wrong-how-to-make-story-points-suck-less-c641c34ce63#7ed1

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events