On the Scrum board we have Sprint insights. The Story points as per Sprint Burndown chart never match with what we actually have assigned to the sprint. I am not sure if this has any configuration that we need to take into consideration.
Hi Archana,
To fix this, we should go back to the roots of the data. Could you show us what you are seeing and where you don't think it matches?
You should check the Estimation in Board settings. Estimation Statistic should be Story Points and Time Tracking should be None (tracking time is estimated by story points).
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.