Configure time per day as ecplained here and GH should pick it up.
https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking
Is this a per project setting or a global setting? I have one project in a different country that I need to track with 6 hours per working day while I want to the rest to remain at the default 8 hours per day, is this possible? how do I do this?
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is a global setting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What happens to other tickets when this changes that already have estimates or time logged? Does the conversion of those estimates just change to use the updated workday hours?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
AI-powered meeting notes keep work moving even if you’re out of the office. Enjoy your well-deserved time off and return refreshed, confident you’ll catch up in no time.
Learn more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.