start date and end date

Ivan Andrieiev
Contributor
September 29, 2022

if i have a date start date and end date, will I be able to compare the number of days between them with the help of some means, and create a separate column in the filter?

1 answer

1 accepted

0 votes
Answer accepted
Melo
Community Champion
September 29, 2022

Hi @Ivan Andrieiev

You can compare the dates with automation for Jira and the result can be added to another CF.

https://support.atlassian.com/cloud-automation/docs/jira-smart-values-date-and-time/

Cheers,

Melo

Ivan Andrieiev
Contributor
September 29, 2022

Hi @Melo 

And there is an article on how exactly it can be used? I don't quite understand.

Melo
Community Champion
September 29, 2022

Sure here is an article with the basics of Automation for Jira

https://www.atlassian.com/software/jira/guides/expand-jira/automation

Let's say you are filling theses fields upon creation

Trigger: Issue Created

Condition: you need to reduce the scope so let's say Project = XYZ and "start date" is not EMPTY and "end date" is not EMPTY 

Action: Select the output field (You need to create on custom field){{[date1].diff([date2]).[unit]}}

Replace date1 and date2 by the date fields you want to compare, unit can be days, hours and etc...

Ivan Andrieiev
Contributor
October 4, 2022

Thank you, I will try.