Hi, Is there a rule for when sub task is shifted to in progress, the parent card is sync to in progress and thereafter start date is updated?
hi @Sean
Welcome to the Atlassian Community!
you can achieve that by creating an automation rule, have the trigger as issue transition and specify inside it (from - to) statuses.
then add a condition that issuetype = subtask
last , open a branch and select parent, and add an action under that branch to edit issue due date and use smart value {{now}}