Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Tempo planner not showing issues already assigned to them

Tadej Breznik
Contributor
January 31, 2023

Hello!

 

Maybe I'm imagining the wrong, but tempo planner is not showing issues under the user, that are currently assigned to them. If I expand the view under the person, there is nothing, and the available time is still full, which is not correct, as some of them are fully occupied, and issues are open with start and end date, original and remaining estimate.

 

What am I missing?

 

Regards.

1 answer

1 accepted

3 votes
Answer accepted
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 31, 2023

Hi @Tadej Breznik and welcome to the community,

Tempo planner will not show you the assigned issues to a user. You have to plan them by dragging and dropping them on the planner calendar, or simply by clicking on a date, choose the appropriate issue and planned time. Assignment of the issue doesn't give you the info on when the assignee will work on the specific issue.

Hope that helps.

Tadej Breznik
Contributor
January 31, 2023

Thank you for the greeting.

Yea it helps, but kinda contradicts the idea of planning, if you don't see whats already planned and automatically imported through open jira issues, and you have to manually input everything for a 50 person company with probably 200+ open issues. To my logic, tasks should be synced (like are with the events of the calendar), and on top of that you do the planning for next weeks and months.

Am I misunderstanding this?

 

Regards.

Like Dave Rosenlund _Trundl_ likes this
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 1, 2023

@Tadej Breznik take a look at this please https://help.tempo.io/cloud/en/tempo-planner/resource-planning/creating-plans-from-jira-issues.html

The above instructions will let you more automatically plan your existing issues. However there are certain prerequisites that need to be met e.g. Assignee, Due Date, and Original Estimate have to be filled already.

Let me know if the above helps. 

Like Dave Rosenlund _Trundl_ likes this
Tadej Breznik
Contributor
February 1, 2023

Yes!

I knew i was missing something :)

Due date. We were working with end date.

 

Thank you Alex!

Like 2 people like this
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 1, 2023

No prob! Glad to be of help!

Like 2 people like this
Tadej Breznik
Contributor
February 1, 2023

Alex, since you were sincerely really helpful, would you mind helping me understand this as well?

 

The Tempo planner takes into account the original estimate, not the remaining estimate.
This means that if someone has in this moment a task open, and the original estimate is, for example, 30 hours, and he has already worked 8 hours, the tempo planner takes into account the occupancy of 30 hours and not 22 hours during the import. For example, if this task has a start date of February 1, 2023, and a due date of February 20, 2023, and the current date is February 5, 2023, where the task was imported into the planner, it will automatically allocate the occupancy by day and plan 30 hours from February 5 to February 20, but not after taking into account, say, 8h which were made in the days between 1.2.2023 and 5.2.2023. Therefore, the use of the tempo plannr is not from point 0 and immediately, but for tasks that are yet to be open correct?

And my issue with this that, or the question remains, lets say the task in undergo and we are in the middle of the task, if it then takes into account the hours already worked (probably not) and allocates according to how much is still done even after the task takes place, taking into consideration other tasks and potential calls and meeting from the calendar import?
I guess probably not, because there is no automatic integration with jira, but a manual update and import, and because the taken time is the original estimate, not the remaining estimate?

 

Thank you!

Like 2 people like this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
atlassian, atlassian government cloud, fedramp, webinar, register for webinar, atlassian cloud webinar, fedramp moderate offering, work faster with cloud

Unlocking the future with Atlassian Government Cloud ☁️

Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.

Register Now
AUG Leaders

Atlassian Community Events