Velocity Chart in JIRA Agile displaying incorrect velocity?

Miguel De Dios February 17, 2014

I've looked at the data and so have a few other folks and 81 Commitment makes sense, but we still can't figure out how JIRA Agile reports 60 for completed in the Sprint: Rice Lake

After doing the math multiple times we've concluded that the true velocity is 51 not 60.

Burndown Chart followed by the Sprint Report for Sprint: Rice Lake

2 answers

0 votes
Rekha Bhaskaran July 20, 2015

hi ,

Did you get any solution for this ?

0 votes
Miguel De Dios February 17, 2014

I can send the images separately in an e-mail, I didn't think they would look that small after previewing. Sorry about that

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, atlassian government cloud, fedramp, webinar, register for webinar, atlassian cloud webinar, fedramp moderate offering, work faster with cloud

Unlocking the future with Atlassian Government Cloud ☁️

Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.

Register Now
AUG Leaders

Atlassian Community Events