When will or how can you get Jira's Task relationships show correctly where you can collapse a Epic like you can now do for Tasks/Sub-Tasks where you can collapse the view of sub-tasks so that you can roll everything up under the Epic?
Hi, similar to your other question that @Kevin Johnson already answered, you'll probably need to look at add-ons for this:
Hi @Dave W
As mentioned above you can do this with Agile Docs (I'm the developer behind it).
You can use it to expand and collapse Epics, Tasks and Sub-Tasks on the one page.
Let me know if this is what you're looking for.
Best Regards,
Rhys
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Dave W
As an alternative, you can also try out our app
Agile Tools : Epic Tree & Time in Status
The app provides you complete Epic Hierarchy for a project with progress at each level. You can view/manage roll up for standard Jira hierarchy. Epic -> User Story -> Subtask
The app also provides Dashboard gadgets for this data.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Dave W ,
As I have already mentioned this feature is not there by default, I'm attaching few reference tickets for this feature.
https://jira.atlassian.com/browse/JSWCLOUD-17275
https://jira.atlassian.com/browse/JSWCLOUD-8726
Regards,
Kevin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.